Quick answer: Yes. A new pool in the Town of Davie requires a permit from the Building Division, with structural, electrical and plumbing applications. Davie asks for more than most Broward cities: an engineer-sealed plan set with soil information, a drainage cross section, a landscape screening diagram for the equipment and, when the lot is in a drainage easement, approval from the local drainage district.
This guide explains who issues pool permits in Davie, what goes into the permit package, the local issues that slow projects down and how the inspections work. Requirements change, so always confirm the current checklist on the Town of Davie structural forms and checklists before submitting.
Who Issues Pool Permits in Davie?
Pool permits in Davie are issued by the Town of Davie Building Division, at 8800 SW 36th Street. Pool applications are reviewed by Planning and Zoning, Structural and Engineering, so the plans need to satisfy zoning setbacks, structural design and drainage at the same time.
What the Davie Pool Permit Package Includes
Based on the Davie residential pool checklist, a typical new pool submittal includes:
- Building permit application, plus structural, electrical and plumbing permit applications.
- Addendum form signed and notarized by the contractor and the owner.
- Recorded Notice of Commencement when the job value is above the threshold, and a signed contract as proof of job value.
- Copy of ownership from the Broward County Property Appraiser.
- Signed and sealed survey (with a survey affidavit if it is more than two years old) and a site plan showing setbacks.
- Complete engineer-sealed plan set including soil conditions (a geotechnical report or soil statement).
- Pool barrier requirements noted on the plans and a completed Pool Safety Act form.
- Electrical drawings with load calculations, overhead conductor clearance noted on the survey and specifications for the pumps, heater, lighting and automation.
- Completed drainage cross section, and a landscape diagram showing how the equipment will be screened.
- Tree affidavit, or a tree removal permit if trees will be removed.
Local Issues That Affect Pool Permits in Davie
Drainage district approvals
Davie is served by several drainage and water control districts. If the pool or deck is in a drainage easement or near a canal or lake, the Town asks for approval from the district that applies, such as the Central Broward Water Control District, the South Broward Drainage District or Tindall Hammock.
Soil information
The Town requires soil conditions as part of the engineered plans. That information also helps design the shell and the dewatering plan.
Larger and rural lots
Davie has many larger lots and equestrian properties. More space makes design easier, but septic systems, wells, utility easements and overhead power lines all need to be shown and respected on the plans.
Equipment screening and trees
Davie asks how the pool equipment will be screened with landscaping and how existing trees are affected, so the site plan has to show both.
Pool Safety Barrier Requirements in Davie
Every new residential pool in Florida must meet the Residential Swimming Pool Safety Act (Chapter 515, Florida Statutes). Before the final inspection, the pool needs at least one approved safety feature, such as:
- A pool barrier (fence, wall or screen enclosure) that meets the Florida Building Code, with self-closing, self-latching gates.
- An approved safety pool cover.
- Exit alarms on all doors and windows that give direct access to the pool.
- Self-closing, self-latching devices on doors that give direct access to the pool.
- A swimming pool alarm that sounds when someone enters the water.
The method you choose is declared on the Pool Safety Act form that is part of the permit package and shown on the plans. If the barrier is a new fence or screen enclosure, it may need its own permit.
Inspections During Construction
Once the permit is issued, the city inspects the pool at key stages. The exact list depends on the scope, but a typical residential pool goes through:
- Steel and bonding, before the shell is sprayed.
- Plumbing, including a pressure test of the pool lines.
- Electrical, for the equipment, lighting and equipotential bonding.
- Deck, when it is part of the permit.
- Final, including the safety barrier or the alarms declared on the Pool Safety Act form.
A Notice of Commencement recorded with Broward County is required for jobs above the state threshold and must be on file before the first inspection.
How Accro GC Handles Your Davie Pool Permit
When you build with Accro GC, the permit is part of the job. We prepare the engineered plans and the survey coordination, complete the safety and owner forms with you, submit the package, answer plan review comments and schedule every inspection until final approval. See how we design and build pools on our Davie pool builders page, or learn more about our pool construction services across Broward County.
Frequently Asked Questions
Do I need a permit to build a pool in Davie?
Yes. Any new in-ground pool requires a building permit and inspections, along with the trade permits for plumbing and electrical work.
Why does Davie ask for a drainage district approval?
Parts of Davie are inside water control or drainage districts that maintain canals and easements. If the work is in or near those easements, the district has to approve it before the Town issues the permit.
Does Davie require a soil report for a pool?
The residential pool checklist asks for soil conditions in the engineer-sealed plan set, either as a geotechnical report or a soil statement from the engineer.
Can I pull the permit myself?
Florida allows owner-builder permits in some cases, but the owner then takes legal responsibility for the work and the licensed trades. Most homeowners have their licensed pool contractor pull the permit.
Request a free estimate or call (954) 934-3379 and we will review your lot, your HOA rules and the permit requirements during the site visit.